LINGERMAN INTERCEPTOR SEWER AND LIFT STATION

Construction Inspection


theconstructo.com
theconstructo.com
 

VS Engineering provided construction management and inspection services for the Lingerman Interceptor Sewer and Lift Station Project in the Town of Avon, IN. The West Central Conservancy District (WCCD) retained VS to provide construction management and full-time construction inspection for the project, including the following contract items:

  • 14,593 LF PVC sanitary sewer pipe installation 
  • 1,405 LF RCP sanitary sewer pipe installation 
  • 1,092 LF pressure class sanitary sewer pipe installation
  • 248 LF force main installation
  • Directional pipe drilling
  • Horizontal pipe boring
  • 70 manhole installations
  • Lift station demolition
  • Lift station installation
  • CCTV of newly installed sanitary sewer pipe
  • Erosion control
  • Restoration activities including trees, shrub, seed and mulch and sod installation
 

VS provided full-time inspection of the project that required much coordination with regulatory agencies, local government officials and residents alike. Full-time inspection was in conformance with the firm's QA/QC program:

  • Daily inspection of contractor's and subcontractor's work to ensure complete conformance with plans and specifications 
  • Quality Assurance testing of all constructed materials
  • Daily reporting of all construction activities, including complete material and manpower records
  • Daily, weekly and monthly report
  • Tracking progress of work on a unit price basis for verification of prime contractor's pay vouchers
  • Maintaining files of all work item invoices and material tickets
  • Regular interaction with design and contractor for clarification and interpretation of contract requirements
  • Availability to residents to answer questions and concerns
  • Communication between designer, owner and prime contractor
  • Final project accounting and all project close-out requirements